Optimising EV charging in collective housing

Ile-de-France Region

2015-2019

10 buildings with approx. 10 EVs each

01-encart
02-encart

Objectives:

Propose connection options for clusters of charging points for some 10 EVs in collective housing.

 

 

Set up a competitive global economic scheme through a commercial operator ensuring “all-inclusive” service, whether in social or private housing.

 

 

Identify metering issues arising from connection downstream from the meter in collective areas of the building.

 

 

Integrate a car-sharing service and test its profitability in collective housing.

 

 

Build up an algorithm for EV charging optimisation in collective housing.

03-logo-2

ACHIEVEMENTS AND LESSONS LEARNED

05-encart-vert
05-picto-vert

Grid-wide roll out ongoing

Charging point connection solutions in collective housing: three connection options have been tested, with dedicated delivery points according to building location and local grid situation (“foot” of the electric conduct, direct grid plugging or sub-metering from the collective meter), and pricing defined accordingly.

 

White paper on “recommendations for installing an EV charging infrastructure in existing collective housing”.

06-encart-bleu
06-picto-bleu

Further development needed before roll out

Testing of charging command-and-control : a smart command and control of EV charging would help optimise costs and grid impact.

 

 

Sub-metering: test of an IT blueprint for automated

sub-metering.

COMPLETED

DETAILS

Where :

When :

What :